Hi, if an enterprise project has started ie it has a % work or duration against it, can you confirm the start date of the project is locked and cannot be moved using Bulk Edit?
Interesting question, I have not tried this before but after just testing now I can see that it doesn’t update the date. Although it also doesn’t get any error!
The behavior is the same as when you edit the Start Date of such a project in a PDP, the date saves without issue, but then when you reopen the project it has reverted.
Hope that helps,
Martin
Author
Posts
Viewing 1 reply thread
The forum ‘Bulk Edit Support Forum’ is closed to new topics and replies.